MANILA, Philippines — The Department of Public Works and Highways (DPWH) will begin the second phase of the rehabilitation of Epifanio delos Santos Avenue (Edsa) on Saturday evening of July 3, 2026, with roadworks set from the Orense area in Makati City to Monumento in Caloocan City.
According to the DPWH, the repair works in intermittent road sections will be carried out until July 23, 2026 and will include the following:
READ: Edsa rehab finally a go: To take 8 months starting Dec. 24
Article continues after this advertisement
Asphalt overlaying: Monday to Friday (10 p.m. to 4 a.m.)
FEATURED STORIES
NEWSINFO
NEWSINFO
NEWSINFO
Asphalt overlaying and concrete reblocking: Friday to Monday (10 p.m. to 4 a.m.)
Drainage and sidewalk improvement activities under phase one: 24/7
For asphalt overlay:
Southbound
July 20-23, 2026: Bus lane from Monumento circle to Edsa McDonalds Caloocan
Northbound
July 6-8, 2026: Bus lane and lane 1 from Guadalupe bus station to Avida Town Center
July 16, 2026: Lane 2 to lane 3 from Guadalupe bus station to Avida Town Center
July 20-21, 2026: Lane 2 to lane 3 from Guadalupe bus station to Avide Town Center
Rotomilling
Article continues after this advertisement
Southbound
July 6-7, 2026: Bus lane from Monumento circle to Edsa McDonalds Caloocan
July 13-24, 2026: Bus lane from Edsa McDonalds Caloocan to Balintawak Global Oil
READ: DPWH nears completion of Edsa phase 1 rehab
Article continues after this advertisement
Northbound
July 3-4, 2026: Bus lane and lane 1 from Guadalupe bus station to Avida Town Center
July 9, 2026: Lane 2 to lane 4 from Guadalupe bus station to Avida Town Center
July 13-15, 2026: Lane 2 to lane 3 from Guadalupe bus station to Avida Town Center
The DPWH said that partial lane closures will be implemented./gsg